I am hoping someone here can shed light on my problem.I am trying to integrate TFS work items and MS Project.What field is mapped from the work item into the duration column of Project?I can change th

I am hoping someone here can shed light on my problem. I am trying to integrate TFS work items and MS Project. What field is mapped from the work item into the duration column of Project? I can change the way I am doing this, but, I had created a custom field Work Item field in TFS. I have the mapping file that TFS uses to map to Project. Here is my Work Item definition:

<FIELD name="EstCodingHours" refname="CustomFields.EstCodingHours" type="Double" 
       reportable="detail">
   <HELPTEXT>Enter estimated number of hours to fix bug</HELPTEXT>
</FIELD>

Here is my mapping definition:

<Mapping WorkItemTrackingFieldReferenceName="CustomFields.EstCodingHours" 
         ProjectField="pjTaskDuration" ProjectUnits="pjHour" />

I can m开发者_如何学运维ap to other fields such as pjTaskDuration1. Is pjTaskDuration read only perhaps? If I can figure out what maps into pjTaskDuration, I can use it instead of my new field EstCodingHours.

Thanks, Scott


The TFS out-of-the-box templates don't map the duration field by default.

Wes Macdonald steps through the process of doing such a mapping in a blog post.